Keeping on (the cycle) Track

Hands up who remembers those heady days of 2013 and 2014 when the cycleway network proposal for Christchurch was first suggested.  The $69 million spend; the completion within 5 years. How things have changed over those last 8 years. $69 million is going to be closer to $300 million and the 5 year completion date more likely to be 18 years.

Mike Yardley – The Press 2013: “A cycling city”

Cr Aaron Keown’s propensity for kite-flying defies all limits, but the free-ranging councillor might have finally stumbled on a nugget of common sense. Keown is right. The $69 million package of 13 city-wide cycleways is a stirring proposition that should be actioned.  Enough of the lip-service and the lofty 30-year strategic plans. Enough of the faffing about.  City Hall could pave our roads in reports, given their compulsive obsession with producing weighty, worthy dust-gathering tomes, that deliver bugger all.  Let’s just do it. Spread over three years, which is as long-term as we are allowed to think in Christchurch, the annual funding provision of $23 million, wouldnt necessarily require a rates increase. It’s a question of priorities. This portfolio of signature cycle routes would immeasurably enhance our credentials as a cycling city. Separating bikes from the general traffic flow benefits all road users. Similarly, a network of separated commuter cycle routes is needed. The CCC and SCIRT must step up their efforts to identify gift-horse opportunities to incorporate separated cycleways into the road reconstruction programme. SCIRT’s Angus Bargh cites the shared-use footpath on Fitzgerald Ave as a recent achievement. May it be the first of many.

How was the ambitious programme going to be funded ?   We’ve been lucky that the Government not only contributed a kickstart steroidal boost to the funding with the Waka Kotahi managed Urban Cycleway Fund  but then along came the Covid ‘Shovel Ready ‘ Project fund. This has meant that the cost to Christchurch Ratepayers has increased from the original $69 million to not too much over $100 million for a $300 million network of superior quality and spread considerably greater than the original expectation. Hard to understand why some City Councillors want to halt the programme at such an advanced stage. A complete network is exponentially better than only half a network. “Do it once, do it properly” is certainly going to pay off in the long run.

What Christchurch is getting however for the extra time and money is ever so slowly transforming the city in a way no one except the everyday cycling fanatics would have predicted back in 2013. “Share an Idea” requested that we rebuild a city that was cleaner, quieter, and greener with less cars plus easier and safer to walk and bike around.

15 years seems like a long time, but when progress is steady and incremental toward a superb, yet realistic end goal, every day of the wait is a 24-hour journey worth taking.

Let’s check last month and see what good news for those who walk and ride a bike around the city has been reported:

    • The Wheels to Wings cycleway in Harewood continues to share information about the options considered and changes made
  • The submissions report for Stage 3 of the Te Ara O-Rakipaoa Nor’West Arc cycleway makes for generally positive reading.
New signals and cycle lanes at Cashmere/Worsleys
  • If you haven’t already travelled along it, the South Express Cycleway Puari ki Niho-toto as far as Main South Road is nearing completion.
South Express cycleway crossing Matipo St
  • The final stage of the Heathcote Express cycleway from The Tannery to Heathcote Valley will start soon.
  • Last but certainly not least is the near-completion of the widened and sealed shared path through Charlesworth Reserve, connecting finally the Rapanui Shag Rock Cycleway Puari ki Rapanui to Ferrymead.
Rapanui – Shag Rock cycleway snaking through Charlesworth Reserve

An updated CCC Cycleway Map which includes these changes will soon become widely available.

Let’s also not forget that almost a year ago the mighty Christchurch Northern Corridor Shared Path  was opened. A popular path to ride if ever there was one.

There have been the all important little improvements happening too. Following some social media activity, the highlighted gnarly bumps on the QE II Drive Shared Path were smoothed over as if by magic only a couple of weeks after this photo was taken. Well worth the 20 year wait.

One  proposed cycleway that seems to have dropped off the radar a little is the Northern Line Cycleway Puari ki Pū-harakeke-nui.  Five years from consultation and there is little obvious activity in the places that matter. One less crucial section has been completed and another is soon to be completed as shown. Off the publicity radar, yes but certainly not forgotten about.

Railway Crossing improvements and connecting Sturrocks Road to Tuckers Road are but two areas needing urgent attention. It is encouraging to see the dollars  allocated in the Long Term Plan for this very important cycleway to enable progress in the coming 12 to 24 months.

The reasons behind the delay are complex. Any comment by me would be little more than unfounded speculation with a smattering of hearsay thrown in. A formal request for comment from official channels may reveal some encouraging information. Is anybody out there who would be able to oblige? A few words in the comments section would be welcome.

So……  2013 to 2021, soon to be 2022. What a long way we have come. What a positive future to look forward to if you enjoy, like me just going about everyday business on a humble bike…

Have you tried out some of the new cycleway developments lately?

5 thoughts on “Keeping on (the cycle) Track”

  1. Re the Northern Line: crossing improvements including signals at Harewood, Langdons, Sawyers are in the works – not sure if final designs or timing is locked in yet. The section Tuckers Rd right through to Styx Mill Rd (excepting Barnes Reserve which is underway now) has a planned start date of August 2022. Seems like the design / access negotiations with Kiwirail have impacted timing.

  2. Typo alert – You say “The Te Ara Ihutai Christchurch Coastal Path completion is progressing also.”
    it’s Christchurch Coastal PathWAY 🙂 And whatever the name, it’s still great and will be even better.

  3. Today 18/11/21 I asked CCC for an update on status and plans for the Northern Line MCR.

    “The final sections” of this MCR were included in CCC’s Newsline story of 8/8/20 – see https://newsline.ccc.govt.nz/news/story/christchurch-cycleways-benefit-from-shovel-ready-funding.

    Six cycle routes will be completed in Christchurch thanks to funding from the Government’s investment in shovel-ready infrastructure as part of the COVID-19 recovery.

    The article (remember it is dated 8/8/20) goes on to say “Construction is expected to start on some of these projects within the next few months, with the remainder beginning in 2021”.

    I do note that there have been works notices for Barnes Reserve, so it looks like something has been happening. If you can enlighten me, pls email me at secretary@spokes.org.nz.

    Thank you
    Chris Abbott